Heavy Industry & Mining · Mining Machinery (Quick Reference)

Mining Dump Truck Selection Parameters

【Selection Parameters】

Rated payload: 20~360 tonnes (depending on the mine size)

Motor power: ≥ 7kW/t (heavy duty uphill)

Maximum gradient: ≥ 15%

【Matchingcalculation】

Excavator bucket capacity: mine car capacity = (3~5) × bucket capacity

Heavy duty speed ≤ 20km/h (mine haul roads)

Tyre life: 2000~4000 hours

Mine Hoist Design Parameters

【Hoisttype】

Single-rope winding: suitable for depths ≤ 600m

Multi-rope friction winding: suitable for depths of 600~2000m

【Wire Rope Calculation】

Safety factor: ≥ 9 when hoisting personnel, ≥ 7.5 when hoisting material

【Braking System】

Disc brake braking torque ≥ 3 times the maximum static torque

Safe braking deceleration: ≤ 5m/s² for personnel, ≤ 7m/s² for material

Mine Ventilation Fan Selection

【Selectionrequirement】

The total mine airflow is calculated from the maximum number of people working underground × 4m³/min per person

Check simultaneously against the airflow required for diluting firedamp

【Air Pressure Calculation】

h=α×L×P×Q²/S³

α is the friction resistance coefficient (0.002~0.01N·s²/m⁴)

【Main Fan Selection】

Axial: high flow, low pressure, easy for forced ventilation

Centrifugal: high flow, high pressure, high efficiency

Standby factor: the main fan must have 100% standby capacity

Mining Excavator Selection Parameters

【Selection】Standard bucket capacities 4~56m³ (large mining shovels), working weight 100~1500t

【Matching】Bucket to mine car capacity ratio 1:3~5

【Recommendation】For 1~5 million tonnes per year select 4~10m³, for 5~20 million tonnes select 10~30m³, above 20 million tonnes select 30~56m³

Underground Mine Drainage System Design

【Pump Configuration】At the normal inflow: 1 duty + 1 standby + 1 on maintenance; at the maximum inflow all pumps run together

【Water Sump】Main sump capacity ≥ 8h of normal inflow, gradient ≥ 0.5%

【Pipework】Drainage pipe velocity 1.5~2.5m/s, suction pipe 0.8~1.5m/s, at least one standby pipeline

Related quick references: Crushing & GrindingMineral Separation & ClassificationConveying & FeedingBuilding Materials & CementIron & Steel MetallurgyThermal Engineering & Energy

Related 3D models: Ready to build it? Download free 3D models & CAD drawings at MOULDL »
MOULDL · Mechanical Engineering Knowledge Base · free self-study reference for machine designers, 3D CAD models at MOULDL