Insufficient Preload Causes Slippage of the Mating Face

E42-020 · Threaded Connection Loosening · Flange Bolted Joint M24 · ★★★

Problem Symptom

Mating face shifted and leaked during the internal pressure test

Root Cause

[Preload Requirement] Sealing requires a specific bearing pressure q=25MPa over an area A=3800mm², so the clamping force must be F=95kN and each bolt must carry at least 19kN.
[Actual Preload] Hand tightening gives only F0=8kN; with a friction coefficient μ=0.15 the anti-slip force is F_f=μF0=1.2kN, far below the requirement.
[Design Omission] The torque was not specified to standard and no gasket was used, so the leak test failed.

Correct Solution

1) Calculate the preload torque in accordance with VDI 2230;
2) Tighten with a torque wrench to M=420N·m;
3) Add a metal spiral-wound gasket;
4) Tighten in a diagonal sequence;
5) Use a hydraulic tensioner (for large sizes);
6) Measure the preload by ultrasonic means;
7) Carry out a pressure test for acceptance;
8) Make the preload torque a mandatory flange assembly inspection item.

Checklist

References

GB/T 912 Steel Pipe Flanges

Related 3D models: Ready to build it? Download free 3D models & CAD drawings at MOULDL »
MOULDL · Mechanical Engineering Knowledge Base · free self-study reference for machine designers, 3D CAD models at MOULDL