Pumping hot water without accounting for the vapour pressure empties the pump

E44-105 · Pump Selection & Cavitation · Hot Water Circulation Pump IRG80-160 · ★★

Problem Symptom

Hot water at 95 degrees Celsius was pumped (Pv=0.084MPa, close to atmospheric pressure), leaving only 0.8m of NPSHa; the pump repeatedly went air-bound and the delivery was intermittent

Root Cause

[Vaporisation] The high temperature raises Pv and lowers NPSHa to the point of vaporisation.
[Calculation] NPSHa=10.33+Hg-hf-Pv/rho*g; at 95 degrees Celsius Pv/rho*g=8.6m, so NPSHa is insufficient.
[Design Omission] Neither the installation height was reduced for the high-temperature medium nor was pressurised priming provided, so the pump emptied.

Correct Solution

1) Lower the installation height or use a below-grade flooded suction arrangement so Hg is -1.0m maximum: with flooded suction the inlet is at positive pressure, so NPSHa rises from 0.8 to at least 3.0m;
2) Install a pressurised priming arrangement at the inlet to hold a steady positive pressure: a high Pv must be compensated by pressure, so this prevents vaporisation;
3) Fit a vent valve on the pump casing to release accumulated gas: trapped gas causes the air binding, so venting keeps the pump full;
4) Select a cavitation-resistant impeller with a large NPSHr margin: high-temperature service is more prone to cavitation, so this keeps the machine running steadily;
5) Keep the suction pipe short and straight to reduce hf: hf takes a large share of the available NPSHa, so a margin is preserved;
6) Cool the medium or run it under pressure: lowering Pv raises NPSHa, so this prevents the pump emptying;
7) Commission the pump and verify continuous delivery with no air binding: the design requirement must be verified by measurement, so this confirms the delivery;
8) Include the vapour pressure of the high-temperature medium in the selection calculation: Pv cannot be ignored, so this prevents recurrence.

Checklist

References

GB/T 5656-2008 Centrifugal Pumps - Technical Conditions (Class II)