Cavitation at the first-stage impeller of a vertical turbine pump

E44-203 · Pump Selection & Cavitation · Vertical Turbine Pump 500LXA · ★★★

Problem Symptom

Cavitation craters 1.5mm deep appeared at the first-stage impeller inlet (the design called for no erosion), the head dropped 8%, the casing produced abnormal noise and the vibration was 4.2mm/s

Root Cause

[Cavitation] Insufficient submergence of the first stage keeps NPSHa below NPSHr, so bubbles collapse at the impeller inlet and erode the metal.
[Calculation] NPSHa=Pa/rho*g-Hs-hf-Pv/rho*g=2.3m against NPSHr of 3.2m, a difference of 0.9m, so bubbles form.
[Design Omission] The first-stage submergence was not checked against the minimum water level and the NPSHa margin was insufficient, so cavitation occurred.

Correct Solution

1) Increase the first-stage submergence to 1.5D or more: every 1m added submergence raises NPSHa by about 0.01MPa, lifting it from 2.3m to at least 4.0m, so the inlet static pressure stays above the vapour pressure and no bubbles form;
2) Check NPSHa against the minimum water level rather than the average level: the low-water condition is the most severe, so this keeps the machine cavitation-free over the whole range;
3) Select an impeller with a lower NPSHr or fit an inducer: the inducer raises the inlet pressure, so NPSHr drops from 3.2 to 2.0m;
4) Reduce the speed so that NPSHr falls with n squared: NPSHr varies as n squared, so a 10% speed reduction lowers NPSHr by about 19%;
5) Use a cavitation-resistant material for the first stage such as duplex steel: cast iron has poor cavitation resistance, so this delays the formation of craters;
6) Add flow guides to the suction passage to prevent maldistribution: maldistribution creates local low pressure, so a uniform flow pattern is obtained;
7) Commission the pump and measure NPSHa while confirming there is no abnormal noise or vibration: the design requirement must be verified by measurement, so this confirms the delivery;
8) Include the first-stage submergence in the cavitation check sheet: the original omission of this item was the root cause, so the design must always include it.

Checklist

References

GB/T 13006-2013 Centrifugal, Mixed-Flow and Axial-Flow Pumps - NPSH