Improper mechanical seal flush plan disturbs the inlet and causes cavitation

E44-219 · Pump Selection & Cavitation · Process Pump ZE100-65-250 · ★★

Problem Symptom

The mechanical seal flush plan 11 took the flush from the discharge and did not return it to the suction, so internal leakage disturbed the inlet, causing slight cavitation and a seal temperature rise

Root Cause

[Cavitation] An improper flush plan design disturbs the local pressure at the inlet and adds to the precursors of cavitation.
[Calculation] The flush return point lies close to the low-pressure region at the inlet and disturbs the flow pattern, so the local pressure momentarily falls below Pv and forms micro-cavitation.
[Design Omission] The flush plan (API Plan) selection was never checked against NPSHa, so the inlet was disturbed.

Correct Solution

1) Select a flush plan suited to the medium and NPSHa (Plan 13 / Plan 23): different plans affect the inlet differently, so the plan is matched to the duty;
2) Locate the flush return point well away from the impeller inlet: a point near the inlet disturbs the flow, so the disturbance is avoided;
3) Use Plan 23 external circulation to avoid drawing from the suction: the suction medium is not taken, so the inlet is undisturbed;
4) Control the flush flow to the mechanical seal requirement: too much disturbs the flow, so the flow is kept appropriate;
5) Re-check that NPSHa at the inlet still meets the requirement after flushing: flushing affects the inlet, so it is reviewed;
6) Install temperature monitoring in the seal chamber: a temperature rise is a sign of internal leakage, so this provides monitoring;
7) Commission the pump and verify the inlet pressure and the seal temperature are steady: the design requirement must be verified by measurement, so this confirms the delivery;
8) Include the match between the flush plan and NPSHa in the design: the original lack of that match was the root cause, so the design must always include it.

Checklist

References

GB/T 13006-2013 Centrifugal Pumps - NPSH