Insufficient straight run at the inlet gives a disturbed flow and cavitation

E44-228 · Pump Selection & Cavitation · Centrifugal Pump IS125-100-250 · ★★

Problem Symptom

Only 1.5d of straight pipe was provided ahead of the pump inlet against 5d required, and the elbow close to the inlet caused maldistribution, raising NPSHr and producing slight cavitation

Root Cause

[Cavitation] The short straight run means the elbow discharge has not stabilised before it reaches the impeller, and the maldistribution creates local low pressure that cavitates.
[Calculation] The velocity distribution after an elbow needs 5d to recover; at 1.5d the flow is maldistributed, the local velocity is high and the local pressure falls below Pv, so cavitation occurs.
[Design Omission] The straight run length at the inlet was not laid out at 5d or more, so the flow pattern was disturbed.

Correct Solution

1) Guarantee a straight run of 5d or more ahead of the pump inlet: a straight run homogenises the flow pattern, so the approach flow is uniform;
2) Where space is limited, fit flow straightening vanes at the inlet: the vanes equalise the flow, so the maldistribution is reduced;
3) Use large-radius elbows to reduce the uneven discharge: a large R gives a better flow pattern, so this mitigates the problem;
4) Avoid a valve or reducer immediately ahead of the inlet: these disturb the flow, so the flow pattern stays steady;
5) Check the local NPSHr under maldistribution: maldistribution raises NPSHr, so the worst case is covered;
6) Fit a straightening grid if necessary: the grid straightens the flow, so the profile is uniform;
7) Commission the pump and verify the inlet pressure and vibration meet the design values: the design requirement must be verified by measurement, so this confirms the delivery;
8) Include the inlet straight run requirement in the design: the original insufficient length was the root cause, so the design must always include it.

Checklist

References

GB/T 13006-2013 Centrifugal Pumps - NPSH