Operating point far from the best efficiency point wastes energy

E44-246 · Pump Selection & Cavitation · Centrifugal pump IS150-125-250 · ★★

Problem Symptom

The operating point sat at 0.65Q (the BEP is at 1.0Q), the efficiency was only 62% against a BEP of 82%, and the long-term off-design operation produced mild cavitation

Root Cause

[Cavitation] An operating point far from the best efficiency point gives a low efficiency, and off-design operation raises NPSHr and the vibration.
[Calculation] At 0.65Q the efficiency falls to 62%, which is 20 points below the BEP of 82%; the off-design inlet flow angle increases, local low pressure appears and mild cavitation follows.
[Design Omission] The selection did not place the operating point near the BEP, so the pump ran inefficiently.

Correct Solution

1) Re-select or adjust the pump so that the operating point falls in the 0.8 to 1.1Q band around the BEP, because the BEP gives both the highest efficiency and the lowest NPSHr, thereby achieving both objectives;
2) Trim the impeller diameter to shift the operating point to the BEP, because trimming shifts the pump curve, thereby aligning the duty point;
3) Use VFD speed control to match the demand and land in the high-efficiency region, because changing speed moves the operating point, thereby raising efficiency;
4) Use staged control of a multi-pump arrangement to keep each pump near its BEP, because staged control is flexible, thereby maintaining high efficiency at all times;
5) Check the operating point efficiency and NPSHr, because deviation affects both indices, thereby quantifying the duty;
6) Avoid long-term extreme off-design operation, because off-design operation cavitates, thereby reducing off-design running;
7) Measure the operating point efficiency during commissioning to confirm compliance, because the design requirement must be verified by measurement, thereby closing out the acceptance;
8) Make landing the operating point on the BEP a mandatory item in the selection report, because the deviation was the root cause, so the design must include it.

Checklist

References

GB/T 13006-2013 Centrifugal Pumps - NPSH