Poorly located inlet pressure gauge leads to a false cavitation assessment

E44-247 · Pump Selection & Cavitation · Centrifugal pump IS80-50-200 · ★★

Problem Symptom

The inlet pressure gauge was installed downstream of an elbow where dynamic pressure disturbed the reading; the reading was 0.015MPa higher than the true value and NPSHa was wrongly judged to be adequate

Root Cause

[Cavitation] The gauge location is disturbed by dynamic pressure so the reading is distorted, NPSHa is misjudged and hidden cavitation results.
[Calculation] A tap downstream of an elbow includes a dynamic pressure of about ρv²/2, that is 0.015MPa; the elevated reading makes the calculated NPSHa falsely high while the pump is in fact cavitating.
[Design Omission] The tap location was not laid out per the standard practice (straight pipe run, away from disturbances), so the reading was distorted.

Correct Solution

1) Locate the gauge tap in a straight length of the inlet pipe (at least 2d away from the disturbance), because this avoids dynamic pressure interference, thereby giving a true reading;
2) Make the tapping hole perpendicular to the pipe wall and burr-free, because burrs disturb the flow, thereby ensuring accuracy;
3) Arrange the tapping point per the static pressure measurement standard, because the standard guarantees accuracy, thereby making the reading trustworthy;
4) Use multi-point averaging where necessary, because a single point is subject to deviation, thereby improving the mean;
5) Check that the gauge range and accuracy match the duty, because an unsuitable range gives a large error, thereby ensuring adequate accuracy;
6) Convert to the true NPSHa using the measured inlet temperature, because NPSHa includes Pv, thereby calculating it correctly;
7) Compare against a reference gauge during commissioning to validate the reading, because the design requirement must be verified by measurement, thereby closing out the acceptance;
8) Incorporate the tap layout standard into the design, because the original location was the root cause, so the design must include it.

Checklist

References

GB/T 13006-2013 Centrifugal Pumps - NPSH