E44-970 · Vessel Strength and Wall-Thickness Deficiency · Pressure vessel · ★★★

Problem Description

Inadequate pressure test, leakage, hazard

Root Cause

[Mechanism] The hydrotest pressure was below the GB/T 150 value; the shell stress never reached the verification level, weld and nozzle defects were missed, and the vessel leaked after commissioning.
[Calculation] Test pressure Pt=1.25P_design[σ]/[σ]_t=1.25×1.6=2.0MPa, but actually only 1.3MPa (0.81×), stress only 0.8[σ], below the threshold that reveals defects.
[Design Omission] The 1.25× design pressure was not used, no pressure hold, and no leak check.

Corrective Solution

1) Run the hydrotest at Pt=1.25×1.6=2.0MPa (was 1.3MPa), since low pressure cannot reveal defects and full pressure does — thus detecting leaks thoroughly;
2) Check that the test pressure is taken at 1.25× design pressure without discount, since a low test pressure misses defects and a correct pressure assures it — thus compliant pressure;
3) Raise the test ratio to 1.25 and hold 30min, since a short hold cannot show seepage and a steady hold reveals it — thus finding micro-leaks;
4) Leak-check after the hold (soapsuds + listening at every weld), since micro-leaks first show as seepage and can be repaired early — thus confirming no leak;
5) 100% visual plus 20% radiography of welds, since defects were uninspected and inspection reveals them — thus finding weld defects;
6) Archive the pressure-test record (pressure-time curve), since an untested vessel has no evidence and a record is traceable — thus keeping the data retrievable;
7) Hold the pressurization rate ≤0.3MPa/min (a sudden ramp damages unsteady parts), since a fast rise triggers cracking and a slow ramp is steady — thus testing smoothly;
8) Write the full-test pressure check into the process card, since the root cause of the missed test was a low pressure with no hold — thus locking it in by process.

Checklist

Reference

GB/T 150.1-2011 Pressure vessels