Knowledge Base › Fluid Systems Error Case › Vessel Foundation Settlement Cracking

Vessel Foundation Settlement Cracking

E44-993 · Vessel Strength and Wall-Thickness Deficiency · Foundation · ★★★

Problem Description

Foundation settlement, cracking, tilt

Root Cause

[Mechanism] Overall or differential foundation settlement bends the shell, adding bending stress that cracks at nozzles/skirt.
[Calculation] Foundation settlement 50mm, added shell moment M=80kN·m, bending σ=80MPa stacks on operating 120MPa = 200MPa, exceeding [σ]=185.
[Design Omission] No foundation reinforcement, no bearing check, and no settlement monitoring.

Corrective Solution

1) Reinforce the foundation (pile + C30 pile cap to raise capacity), since settlement cracked and a reinforced foundation stabilizes — thus preventing cracking;
2) Check foundation bearing capacity (≥200kPa, actual 130kPa — reinforce), since a weak foundation settles and a capacity check raises it — thus stabilizing the support;
3) Add pile foundations (6×Φ400 piles, evenly distributed), since soft ground settles and piles carry the load — thus resisting settlement;
4) Equalize support loads (even filling), since bias cracks and equal load levels it — thus distributing load;
5) Perform settlement monitoring (level at each point, difference ≤10mm), since cracking first shows as settlement and can be adjusted early — thus monitoring settlement;
6) Run a water-filling test (1.0× liquid level held), since the crack came from an unvalidated design and measurement confirms stability — thus setting capacity by data;
7) Hold fill rate ≤2m/h (fast filling biases the load), since a fast rise induces bias and a slow one equalizes — thus filling smoothly;
8) Write the foundation reinforcement and load check into the calculation book, since the settlement-crack root cause was the unreinforced foundation and unchecked bearing — thus locking it in at design.

Checklist

Reference

GB/T 150.1-2011 Pressure vessels