E44-357 · Water Hammer and Pressure Surge · Straight pipe 1200m long, blind end · ★★★
Wave reflection and stacking in a long straight pipe raised the blind-end Δp=1.6MPa beyond the allowable 1.0, bulging the blind-end head.
[Mechanism] The wave reflects fully at the blind end and stacks with the incident wave, doubling the pressure.
[Calculation] Δp=1.6 exceeded the allowable limit and caused bulging.
[Design Omission] No staged pressure relief and no wave control were provided, leaving the straight pipe to reflect the hammer.
1) Fit a relief valve at the blind end to limit Δp≤1.0, because reflection stacking drove it to 1.6 beyond the limit and bulged the head; hence relief to cap the peak;
2) Install a surge arrester mid-pipe to cut the wave, because waves are strong in a long pipe; hence wave cutting;
3) Check 2L/c against the closure time to identify the reflection regime, because length causes reflection; hence reflection check;
4) Replace the blind end with a cushioned head, because a hard end reflects strongly; hence cushioning;
5) Close the valve slowly to avoid direct hammer, because fast closure causes it; hence slow closure;
6) Raise the pipe pressure rating or split the pressure, because the allowable is low; hence higher rating;
7) Use water-hammer simulation to locate the peak point, because hidden peaks are hard to spot; hence simulation;
8) Write reflection protection into the design, because the lack of wave control was the root cause of the hammer; hence design control.
GB/T 32284-2015 Code for design of pump stations - Water hammer protection