E44-168 · Two-Phase Flow and Air Binding · Elevated Water-Supply Line · ★★
The high point was not vented; an air plug cut the flow from 100m³/h to 45m³/h.
[Air Plug] Gas accumulates at the high point and blocks the flow.
[Flow Restriction] The air plug reduces the flow passage area.
[Design Omission] No automatic vent and no slope alignment — air binding.
1) Fit an automatic vent at the highest point; accumulated gas blocked the flow and halved it, so vent the gas to restore flow;
2) Slope the piping at 0.002 toward the vent; flat slope traps gas, so slope for unobstructed venting;
3) Add an air collector at the high point to gather and vent; localized gas is hard to bleed, so collect it first;
4) Fill and vent the piping before pump start-up; the line starts air-rich, so fill and bleed fully;
5) Add flow monitoring to detect air binding; a sudden flow drop is the warning, so monitor the flow;
6) Test the vent valve responsiveness periodically; a stuck valve fails, so inspect on schedule;
7) Test-run and measure flow recovery to at least design value; the design requires measured verification, so confirm at handover;
8) Write venting into the piping design; the missing vent was the root cause of air binding, so design must include it.
GB/T 20801-2020 Pressure piping code