E44-515 · Heat Exchanger Fouling and Insufficient Heat Transfer · Milk Tank Jacket Stainless Steel · ★★
Jacket water scale, slow warm-up, insufficient sterilization
[Mechanism] Hard-water scale deposits on the jacket.
[Calculation] Rf=0.3 lowers K, extends warm-up time by 30%, and leaves sterilization temperature insufficient.
[Design Omission] No water softening and no cleaning, so scale forms.
1) Soften jacket water to keep Rf<0.1; hard-water calcium scale bonds to the jacket (Rf=0.3, warm-up +30%, insufficient sterilization temp), so softening lowers Rf and restores K;
2) Schedule acid descaling (each shift / weekly); scale thickens and hardens, so periodic acid cleaning restores heat transfer;
3) Monitor warm-up time (vs. baseline); scale slows warm-up as a visible symptom, so timing warns of scaling;
4) Fit a sterilization-temperature alarm (≥ setpoint); scale leaves temperature insufficient and sterilization incomplete, a safety risk, so the alarm prevents it;
5) Raise jacket-water velocity to prevent settling; calcium scale settles in low-velocity zones, so higher velocity suppresses it;
6) Dose food-grade scale inhibitor; crystal nuclei bond to the wall and form scale, so inhibitor reduces deposition;
7) Inspect wall thickness on schedule (borescope / thickness gauge); under-scale corrosion changes wall thickness, so inspection guides cleaning;
8) Write softening and acid cleaning into the milk-tank procedure; the original design omitted softening and scheduled cleaning, the root cause of scale, so the procedure closes the loop.
GB/T 151-2014 Heat exchangers