Knowledge Base › Fluid Systems Error Case › Industrial Wastewater Heat Exchanger Suspended-Solids Blockage

Industrial Wastewater Heat Exchanger Suspended-Solids Blockage

E44-548 · Heat Exchanger Fouling and Insufficient Heat Transfer · Industrial Wastewater Heat Exchanger - Tube · ★★

Problem Description

Suspended solids deposit and block, Δp rises, flow drops

Root Cause

[Mechanism] Suspended solids jam the tubes.
[Calculation] High SS causes 40% of holes to jam, v rises, Δp=0.18, and flow drops.
[Design Omission] No pre-sedimentation and no flushing were provided, causing suspended-solids blockage.

Corrective Solution

1) Pre-sediment wastewater to remove suspended solids (clarifier / hydrocyclone desanding, SS≤50 mg/L); because suspended solids jam 40% of holes, v rises, Δp=0.18, and flow drops, pre-sedimentation removes solids and restores the flow passage;
2) Schedule backwashing (reverse flush each shift, force-flush when Δp>0.15 MPa); because solids buildup reduces flow area and pressure rise precedes complete blockage, periodic backwashing removes solids;
3) Add a differential-pressure alarm (trigger when Δp>0.18 MPa); because suspended-solids blockage raises Δp before flow visibly drops, this gives early warning of the blockage trend;
4) Raise flow velocity (≥1.2 m/s) to prevent settling; because suspended solids settle and deposit in low-velocity zones and jam tighter over time, higher velocity reduces residence time and suppresses deposition;
5) Enlarge tube diameter (≥ design lower limit +2 mm); because narrow tubes catch solids and cannot be cleaned thoroughly, wider tubes facilitate flushing;
6) Schedule solids-thickness inspection (borescope / visual every two months); because solids gradually thicken and worsen the Δp rise and flow drop, quantitative measurement guides backwashing;
7) Add return-loop filtration (filter the waste-liquid return line); because more solids mean re-deposition and return filtration reduces loading, return-line filtration suppresses blockage;
8) Write pre-sedimentation and backwashing into the industrial wastewater procedure; because the original design omitted sedimentation and flushing, the root cause of solids buildup, the procedure enforces control.

Checklist

Reference

GB/T 151-2014 Heat exchangers