Paper Mill Black Liquor Heat Exchanger Fouling

E44-552 · Heat Exchanger Fouling and Insufficient Heat Transfer · Black Liquor Heat Exchanger - Plate · ★★

Problem Description

Black liquor silica scale deposits, K drops, blockage, weak evaporation

Root Cause

[Mechanism] Silica salts precipitate from black liquor and deposit.
[Calculation] Rf=0.4 causes K to drop by 40%, 30% blockage, and weak evaporation.
[Design Omission] No silica control and no cleaning were provided, causing fouling.

Corrective Solution

1) Pre-treat black liquor to reduce silica (green-liquor silica removal / add silica-scale inhibitor, SiO2≤ limit); because silica salts precipitate from black liquor and Rf=0.4 drops K by 40%, causes 30% blockage and weak evaporation, silica reduction suppresses crystallization and restores K to preserve evaporation;
2) Schedule cleaning to remove scale (caustic wash / high-pressure flush per batch, clean immediately when Δp>0.1 MPa); because silica scale buildup causes blockage and K drop, periodic cleaning restores the flow area;
3) Add K monitoring (alarm when K drops by 10%); because fouling first lowers K before evaporation weakens, monitoring K gives early warning and guides cleaning;
4) Raise flow velocity (≥1.5 m/s) to prevent settling; because silica salts settle and deposit in low-velocity zones and harden over time, higher velocity reduces residence time and suppresses deposition;
5) Change to non-stick surfaces (polished / PTFE coating); because silica readily deposits on rough surfaces and non-stick surfaces reduce deposition, changing material suppresses silica fouling;
6) Control concentration to prevent supersaturation (concentration≤ saturation lower limit); because supersaturation causes silica to precipitate and deposit, concentration control suppresses precipitation;
7) Schedule scale-thickness inspection (measure thickness / visual every two months); because silica gradually thickens and worsens the K drop and blockage, quantitative measurement guides cleaning;
8) Write silica reduction and cleaning into the black liquor procedure; because the original design omitted silica control and cleaning, the root cause of silica fouling, the procedure enforces control.

Checklist

Reference

GB/T 151-2014 Heat exchangers

Related model download:Understood the principle and ready to try?Go to MOULDL to download related 3D models and CAD drawings for free »