Knowledge Base › Fluid Systems Error Case › Heat Exchange Tube Fouling Reduced Efficiency

Heat Exchange Tube Fouling Reduced Efficiency

E44-1063 · Heat Exchanger Fouling and Insufficient Heat Transfer · Heat Exchange Tube · ★★

Problem Description

Fouling, efficiency drop, temperature rise

Root Cause

[Mechanism] Fouling on the inner wall of heat exchange tubes increases thermal resistance, lowers the overall heat transfer coefficient K, and results in insufficient heat transfer.
[Calculation] Fouling thickness 1.5 mm, fouling resistance Rd=0.0005 m²K/W, K drops from 800 to 520 W/m²K, heat duty drops by 35%, outlet temperature 8℃ low.
[Design Omission] No fouling removal, no scale inhibitor, and no water-quality control were provided.

Corrective Solution

1) Mechanically / chemically remove fouling (high-pressure water + acid pickling); because fouling lowers K and cleaning restores K, this raises efficiency;
2) Verify the overall heat transfer coefficient K≥ design value (actual 520, should be 800); because low K causes poor efficiency and checking K reveals it, this quantifies the problem;
3) Add a scale inhibitor (corrosion-inhibiting scale treatment); because fouling reduces efficiency and inhibition slows it, this suppresses fouling;
4) Stabilize and raise flow velocity (v=1.5 m/s instead of 0.8); because low velocity causes fouling and raising it slows fouling, this suppresses fouling;
5) Perform a heat-transfer test (measure K and temperature rise); because efficiency was never verified and direct measurement confirms it, this determines efficiency from data;
6) Install inlet/outlet temperature-difference monitoring (alarm on temperature drop); because fouling first shows up as a temperature drop, this monitors efficiency and gives early warning;
7) Control water quality in operation (hardness≤150 mg/L); because hardness causes fouling and quality control slows it, this prevents fouling during operation;
8) Write fouling removal and K verification into the specification; because the root cause of efficiency loss is the lack of cleaning and water-quality control, the specification enforces control.

Checklist

Reference

GB/T 151-2014 Heat exchangers

Related model download:Understood the principle and ready to try?Go to MOULDL to download related 3D models and CAD drawings for free »
MOULDL · Mechanical Engineering Knowledge Base · free self-study reference for machine designers, 3D CAD models at MOULDL