E44-734 · Uneven Flow Distribution · Distributor · ★★
Blockage deviation, uneven distribution
[Mechanism] Blockage deviates the flow.
[Calculation] Blockage makes the distribution uneven.
[Design Omission] No cleaning, no filter, and no inspection were provided, so the nozzles clog.
1) Provide upstream filtration against blockage (100μm, protect the nozzles), because the original blockage made the nozzle flows differ by >25%, thereby filtering and evening the distribution;
2) Clean the nozzles at fixed intervals (every shift, remove coke), because deposits cause deviation and cleaning restores flow, thereby cleaning the nozzles;
3) Verify the flow of each nozzle (calibrate, deviation ≤5%), because a difference leaves the distribution uneven and verification restores accuracy, thereby verifying the flow;
4) Standardize the nozzle orifices (same diameter, tolerance ±0.02mm), because an orifice difference causes deviation and standardization evens it, thereby standardizing the orifices;
5) Monitor the blockage (observe the spray, clean on blockage), because gradual blockage is invisible and monitoring catches it, thereby giving early warning;
6) Keep the medium clean (filtration, NAS9), because dirt causes blockage and control keeps it clean, thereby controlling cleanliness;
7) Run a distribution test (dye visualization, accept when even), because the lack of testing caused the deviation and testing verifies it, thereby testing the distribution;
8) Write the filtration and nozzle cleaning into the maintenance card (nozzle cleaning interval), because the missing filtration was the root cause and freezing it into the maintenance card enforces control.
GB/T 20801.3-2020 Design code for industrial metallic piping