Knowledge Base › Fluid Systems Error Case › Disordered Flow Distribution at Startup

Disordered Flow Distribution at Startup

E44-769 · Uneven Flow Distribution · Startup · ★★

Problem Description

At startup, the branch flows were disordered, deviation >25%, wrong sequence

Root Cause

[Mechanism] Startup was out of sequence and the valves opened together.
[Calculation] Opening together makes the branches rob flow, biasing it >25% and disturbing one another.
[Design Omission] Nothing was sequenced on startup and nothing was adjusted, so the sequence was wrong.

Corrective Solution

1) Define a startup sequence (open branch by branch from lowest to highest resistance, interval ≥10s), because opening together made the branches rob flow and bias it >25% with mutual disturbance, thereby starting in sequence and distributing evenly;
2) Open the valves slowly against surges (opening rate ≤5%/s), because an abrupt opening causes disorder and a slow one steadies it, thereby preventing disorder by slow opening;
3) Verify each branch's startup flow (measure and balance each branch's flow after startup), because a difference causes disorder and calibration equalizes it, thereby distributing the flow evenly by calibration;
4) Provide time-delay staggering (stagger the pumps/valves in time), because starting together superposes and causes disorder and staggering disperses it, thereby steadying by delay;
5) Check the startup state (monitor each branch's flow, alarm above 15% deviation), because gradual disorder starves some branches and early detection helps, thereby monitoring startup;
6) Run a startup test (simulate the startup sequence at no load and record each branch's flow), because the omitted test let the disorder go unnoticed and the operation ran abnormally, thereby proving even distribution;
7) Control the total flow (raise the total flow smoothly with startup), because a sudden change breaks the distribution and steadiness preserves it, thereby steadying the total;
8) Write the sequenced startup and slow opening into the operating card, because the omitted sequence was the root cause of the startup problem and the operating card enforces it, keeping the startup even.

Checklist

Reference

GB/T 20801.3-2020 Design code for industrial metallic piping

Related model download:Understood the principle and ready to try?Go to MOULDL to download related 3D models and CAD drawings for free »
MOULDL · Mechanical Engineering Knowledge Base · free self-study reference for machine designers, 3D CAD models at MOULDL