Knowledge Base › Fluid Systems Error Case › Overflow from a Reactor Because the High-Level Interlock Was Not Commissioned

Overflow from a Reactor Because the High-Level Interlock Was Not Commissioned

E44-033 · Level Control Failure · Reactor · ★★★

Problem Description

The high-level interlock was not commissioned, so the reactor overflowed and injured one person, stopping production for a day

Root Cause

[Interlock Failure] The contacts of the level switch were loose and did not actuate, so the high-high level did not stop the feed.
[Overflow] Overfilling caused the material to spill.
[Design Omission] No SIL assessment was done and the interlock was not function-tested periodically; the uncommissioned interlock caused the overflow.

Corrective Solution

1) Design and commission the high-high level interlock to its SIL rating, because the uncommissioned interlock caused reactor overflow, injury, and a production stop, thereby safeguarding to the SIL;
2) Provide redundant dual-channel level switching, because a single switch with loose contacts does not actuate and fails, so dual channels raise reliability;
3) Function-test the interlock periodically, because loose contacts develop gradually and testing catches them early, thereby testing on schedule;
4) Hard-wire the feed valve to the interlock, because hard wiring is faster and more immune to interference than software interlocking, thereby cutting off directly;
5) Provide overflow collection and emergency discharge, because any overflow is then collected and the harm reduced, thereby providing an emergency fallback;
6) Give the operator a high-level alarm prompt, because the alarm allows timely manual intervention, thereby protecting by both people and equipment;
7) Keep interlock actions traceable, because records aid accident analysis and prevent recurrence, thereby providing traceability;
8) Include interlock testing in the safety management system, because the omitted testing was the root cause of the uncommissioned interlock and the system must constrain it.

Checklist

Reference

GB/T 21109-2010 Safety instrumented systems for the process industry sector — Functional safety