Knowledge Base › Fluid Systems Error Case › Plugged Impulse Line on DP Level Transmitter Causing a False Low

Plugged Impulse Line on DP Level Transmitter Causing a False Low

E44-080 · Level Control Failure · DP Level Transmitter · ★★

Problem Description

The plugged impulse line delayed the level indication and gave a false low of 0.4m, so make-up fell short and the supply ran out

Root Cause

[Plugged Impulse Line] The plugged impulse line distorts the differential-pressure transfer, so the indication lags.
[Calculation] The plugging makes the transfer lag, displaying a false low of 0.4m.
[Design Omission] No impulse-line purging was provided and nothing was cleared periodically, so plugging caused a false low.

Corrective Solution

1) Provide impulse-line purging against plugging (timed or continuous air/steam purge), because media congealing plugs the transfer and purging keeps it clear, thereby keeping the differential-pressure transfer undistorted and the indication accurate;
2) Clear and flush the line at intervals, because plugging is gradual and periodic clearing prevents a false low, thereby maintaining accuracy;
3) Compare dual transmitters (two meters on the same source), because plugging on a single meter is hard to notice and a deviation alarm on the two meters exposes it, thereby detecting it early;
4) Heat-trace congealing media, because congealing is the root cause of plugging and heat tracing prevents it, thereby preventing plugging at the source;
5) Verify the display against the remote reading (field vs DCS), because the false low of 0.4m needs comparison and verification corrects it, thereby confirming the true level;
6) Provide a low-level alarm, because the false low can run the supply out and the alarm prevents it, thereby protecting the supply;
7) Prove on trial run that the display is accurate (compare with the gauge glass), because the level gauge's job is accuracy and the trial run provides the measurement, thereby accepting the installation;
8) Include purging in the instrument design, because the omitted purging plugged the line and gave a false low, so purging should be laid out at the design stage.

Checklist

Reference

HG/T 21581-2010 Instrument installation drawings