Weighing Module Foundation Settlement

E44-619 · Level Control Failure · Weighing Module · ★★

Problem Description

Foundation settlement, reading deviation

Root Cause

[Mechanism] Foundation settlement skews the weight reading.
[Calculation] The settlement causes the deviation.
[Design Omission] The foundation was not consolidated, it was not calibrated, and it was not inspected, so it settled.

Corrective Solution

1) Consolidate the foundation against settlement (reinforced concrete foundation, capacity ≥1.5 times the total weight, settlement <2mm), because the original soft foundation made the tank settle unevenly, uneven load on individual modules skewed the weighing (e.g., by 0.5%FS), and consolidating the foundation evens the load, thereby restoring accurate weighing;
2) Calibrate the zero and tare (calibrate with an empty tank, error ≤0.1%FS), because settlement causes zero drift and calibration corrects it, thereby restoring accuracy;
3) Choose a settlement-resistant support (steel saddle plus M24 anchor bolts), because a soft foundation settles and the steel support spreads the load, thereby preventing settlement;
4) Level the load on the three modules (load difference between the modules <1%), because uneven load settles unevenly and leveling the load evens it, thereby reducing the deviation;
5) Control temperature to prevent expansion-induced settlement (provide sliding between the foundation and the tank so expansion does not lift it), because thermal expansion lifting the tank falsifies the weighing and sliding relieves the load, thereby steadying the reading;
6) Check the settlement (measure the foundation elevation monthly, correct once settlement >2mm), because gradual settlement increases the deviation and inspection catches it early, thereby allowing timely consolidation;
7) Perform a full-span calibration (calibrate at full tank, error ≤0.5%FS), because settlement deviates the whole span and span calibration corrects it, thereby confirming accuracy;
8) Write the foundation consolidation and zero calibration into the maintenance card, because the omitted consolidation was the root cause of the settlement and freezing them into the maintenance card enforces maintenance.

Checklist

Reference

GB/T 7723-2017 Weighing instruments