Knowledge Base › Fluid Systems Error Case › Tank Foundation Settlement Causing a Reading Offset

Tank Foundation Settlement Causing a Reading Offset

E44-647 · Level Control Failure · Storage tank · ★★

Problem Description

Foundation settlement, reading deviation

Root Cause

[Mechanism] The settled tank foundation offsets the reading.
[Calculation] The settlement causes the deviation.
[Design Omission] The foundation was not consolidated, it was not calibrated, and it was not inspected, so it settled.

Corrective Solution

1) Strengthen the tank foundation against settlement (a ring-wall foundation with reinforcement, settlement <2mm): because the original soft foundation tilted the tank and offset the level gauge zero (e.g. 0.3%FS off), strengthening the foundation levels it so the weighing or the level returns to accuracy;
2) Calibrate the zero with tare (empty-tank calibration): because settlement offsets it and calibration corrects it, accuracy is restored;
3) Set up settlement monitoring (survey reference points periodically, settlement rate <1mm/month): because gradual settlement increases the offset and monitoring gives early warning, it is strengthened in time;
4) Even the leg loads (load difference between the legs <1%): because uneven loading settles unevenly and even loading levels it, the offset is reduced;
5) Control the filling rate (≤1m/h): because fast filling settles unevenly and limiting the rate evens it, the tank is steady;
6) Check the settlement (survey the elevations monthly): because gradual settlement offsets it and checking gives early warning, it is strengthened in time;
7) Calibrate the full span (full-tank calibration): because settlement offsets the whole range and calibrating the span corrects it, it is confirmed;
8) Write the foundation strengthening and zero calibration into the maintenance card: the original lack of strengthening was the root cause of the settlement, so the card locks it in and maintenance governs it.

Checklist

Reference

GB/T 50341 tank code