E44-136 · Piping Supports and Thermal Expansion · Hot-water heating pipe Π-bend expansion joint · ★★
Pre-stretch only 30% (100% required); at hot state the expansion joint offset 80mm and hit the adjacent pipe, shearing the support
[Insufficient Pre-stretch] A small pre-stretch leaves too little hot-state compensation allowance.
[Offset] ΔL=αLΔT=14e-6×80×95=0.106m; without pre-stretch the whole displacement must be absorbed by the joint.
[Design Omission] No 100% pre-stretch was applied and no offset calculated — causing the pipe collision.
1) Install the Π-bend expansion joint with 100% pre-stretch: because a small pre-stretch left too little hot-state allowance and the 80mm offset hit the pipe, full pre-stretch absorbs the displacement;
2) Verify the hot-state offset ≤ the allowable: because ΔL=0.106m must be absorbed by the joint, accurate calculation prevents collision;
3) Verify the anchor support for the thrust: because the thrust sheared the support, it is checked with F=EAΔL/L;
4) Set guide supports on both sides of the joint: because the guides make the displacement follow the arms, it does not offset;
5) Leave ≥100mm thermal-displacement clearance to the adjacent pipe: because the offset hits the pipe, clearance is provided;
6) Mark the cold pre-stretch traceably: because an omitted pre-stretch is hard to find, the mark allows verification;
7) Measure the offset and clearance at hot trial run: because the design requires measurement, delivery is confirmed;
8) Include the pre-stretch in the installation procedure: the original 30% only was the root cause of the offset, so the procedure governs it.
GB/T 20801-2020 Pressure piping code