E44-803 · Piping Supports and Thermal Expansion · Support Pier · ★★★
Support pier settlement >30mm, pipe bent, cracking
[Mechanism] Settlement of the support-pier foundation bends and cracks the pipe.
[Calculation] A settlement >30mm drives the additional bending stress in the pipe above the allowable and cracks it.
[Design Omission] Neither was the foundation stabilized nor settlement monitored — so the foundation must be stabilized.
1) Stabilize the support pier against settlement (compact the foundation + reinforced-concrete pier): because the original settlement >30mm drove the pipe's additional bending stress above the allowable and cracked it, stabilizing the pier secures the pipe;
2) Provide settlement monitoring (measure the pier elevation periodically, alarm at settlement >10mm): because progressive settlement brings cracking closer and early awareness helps, settlement is monitored;
3) Check the pier foundation capacity (foundation bearing capacity ≥ pipe weight ×2): because a weak foundation settles and the check ensures adequacy, the capacity is checked;
4) Add reinforced concrete (reinforcement ratio ≥0.2%): because soft ground settles and reinforcement stabilizes it, reinforcement is added;
5) Inspect the settlement (survey with a level, alarm at settlement >20mm): because progressive settlement increases the bending and early awareness helps, settlement is inspected;
6) Control the filling rate (fill in stages to slow the settlement): because too fast settles and slow filling keeps it under control, the rate is limited;
7) Perform a bearing test (hydrostatic test to check the pier settlement / pipe bending): because the original lack of testing left the cracking undiscovered, the test reveals the strain, so bearing is tested;
8) Write the pier stabilization and monitoring into the assembly card: the original lack of stabilization was the root cause of the settlement, so assembly controls the work and the pier does not settle.
GB/T 17116.1-2018 Pipe supports and hangers