E44-804 · Piping Supports and Thermal Expansion · Expansion Joint · ★★★
Blind-flange force unrestrained, expansion joint shifted, destabilized
[Mechanism] With no thrust-restraint pier to carry the blind-flange force, the expansion joint shifts.
[Calculation] The blind-flange force F=πD²/4×P drives the displacement > the design value and destabilizes the joint.
[Design Omission] Neither restraint nor a pier was provided — so the force must be carried.
1) Provide a thrust-restraint pier to carry the blind-flange force (the pier carries F=πD²/4×P, shear capacity ≥1.5 times): because the original lack of restraint drove the expansion-joint displacement > the design value and destabilized it, carrying the force stabilizes the joint;
2) Check the blind-flange force (calculate F from the design pressure): because excess pushes and the check reveals it, the force is checked;
3) Add a thrust frame (limit the axial movement of the expansion joint): because thrust shifts the joint and the frame stops it, thrust is stopped;
4) Weld the anchorage firmly (weld the pier to the pipe anchor plate): because looseness shifts and welding secures it, it is welded;
5) Inspect the thrust (displacement-mark monitoring, alarm when movement > design): because progressive thrust damages the joint and early awareness helps, the thrust is inspected;
6) Perform a thrust test (pressurize and record the expansion-joint displacement): because the original lack of testing left the failure undiscovered, the test reveals the bearing capacity, so thrust is tested;
7) Control the pressure ramp to prevent rapid change (raise ≤0.1MPa/s): because a rapid change pushes and a slow one keeps it under control, the pressure is controlled;
8) Write the force carrying and thrust stopping into the assembly card: the original lack of restraint was the root cause of the blind-flange force, so assembly controls the work and the joint does not shift.
GB/T 12777-2019 Metal bellows expansion joints