E46-014 · Welding Process & Distortion · Large Component · ★★
The tack welds were too short and too shallow; during flipping assembly they separated and the parts misaligned, forcing rework
[Mechanism] An insufficient tack-weld length makes the temporary fixing weak; it separates under load when the part is flipped.
[Calculation] A tack-weld length under 30mm gives insufficient load capacity; the parts separate and misalign when flipped.
[Design gap] The tack-weld length was not set according to the component size.
① Sufficient tack-weld length: make the tack weld at least 50mm long to ensure the temporary fixing is secure
② Sufficient penetration: the tack weld should penetrate into the base metal to ensure joint strength
③ Even spacing: space the tack welds evenly so the load is distributed evenly
④ Clean slag before welding: clean the surfaces to be welded before tack welding to ensure fusion
⑤ In-process inspection: check for separation and correct it early
⑥ Use lifting gear for flipping: use lifting gear when flipping large components to avoid tack-weld separation
⑦ Tack verification: confirm the tack welds are secure by a load-bearing test
⑧ Standardize process: write the tack-welding specification into the welding procedure specification (WPS), controlling at the source
GB/T 19866-2005 General principles for welding procedure specification and qualification