E46-405 · Commissioning & Run-In · Hydraulic power unit · ★★
The hydraulic power unit was first commissioned without bleeding the air; when the cylinder moved the piping emitted banging cavitation noise, the cylinder crept and the seal ring failed early.
[Mechanism] Air trapped at the high points of the piping is compressed; the bubbles collapse and produce cavitation impact.
[Calculation] When the entrained air volume exceeds 1% the oil's bulk modulus drops sharply and the response lags.
[Design gap] No bleed valve was provided, nor was the bleeding sequence followed.
① Bleed high points: loosen the bleed valve at each high point until the oil flows continuously without bubbles, then retighten
② Low-pressure circulation: jog at low pressure first to fill the piping with oil and drive out the residual air
③ Cycle each cylinder: stroke each cylinder fully several times to expel the air inside
④ Judge by sound: listen to the pump and valves for cavitation noise and re-bleed if abnormal
⑤ Check oil level: after bleeding, top up to the midline of the level gauge to prevent air intake
⑥ Contamination check: after bleeding, take an oil sample for water or air and change the oil if out of spec
⑦ Quality verification: confirm acceptance by absence of cavitation noise and steady cylinders, confirmed by data
⑧ Standardize process: write the bleeding steps into the hydraulic commissioning sheet, controlling at the source
GB/T 3766-2015 General technical conditions for hydraulic systems