E46-406 · Commissioning & Run-In · Three-phase motor · ★★
A newly installed three-phase motor was started under load without confirming the rotation direction; running in reverse loosened the pump impeller, the mechanical seal leaked water and the unit shut down.
[Mechanism] Reversed three-phase sequence makes the rotor run backward, loosening or reversing unidirectional load parts.
[Calculation] On reversal the axial force reverses, unscrewing and loosening the thread-locked impeller.
[Design gap] No no-load jog was done to confirm the rotation direction.
① Jog to confirm: jog at no load first to check the direction, and load only when it matches the marking
② Check the phase sequence: verify the three-phase sequence with a phase-sequence meter and swap any two leads if wrong
③ No-load first: after confirming the direction, run unloaded for 30 minutes and measure the temperature rise
④ Retighten: retighten the impeller lock nut before loading to prevent loosening on reversal
⑤ Measure current: measure the no-load current and investigate for stall if it exceeds the rated value
⑥ Clear marking: mark the rotation arrow on the terminal box to prevent miswiring
⑦ Quality verification: confirm acceptance by rotation direction and no-load data, confirmed by data
⑧ Standardize process: write the jog confirmation into the motor test-run steps, controlling at the source
GB/T 755-2008 Rotating electrical machines — Rating and performance