E46-409 · Commissioning & Run-In · Reciprocating compressor · ★★★
The multistage compressor was commissioned straight up to the rated discharge pressure; the final-stage temperature surged past the limit, the valve plates deformed and leaked, and the unit shut down.
[Mechanism] Unbalanced stage pressures make the final-stage pressure ratio too high, and the discharge temperature exceeds what the material allows.
[Calculation] When a single-stage pressure ratio exceeds 3 the discharge temperature tops 180℃ and the valve plates anneal.
[Design gap] The pressure was not raised stage by stage per the interstage pressure curve.
① Raise stage by stage: raise the pressure to the interstage design values one step at a time, letting each stage stabilize before the next
② Control the ratio: keep each stage's pressure ratio below 3 and throttle back if it is exceeded
③ Measure temperature: reduce load as soon as any stage's discharge temperature exceeds 150℃
④ Check valves: after reaching pressure, check each stage's valves for leakage noise
⑤ Check water flow: confirm the interstage cooling water flow is sufficient to bring down the discharge temperature
⑥ Record all: record each stage's pressure and temperature, keeping a baseline
⑦ Quality verification: confirm acceptance by interstage pressure and temperature, confirmed by data
⑧ Standardize process: write the pressurization curve into the commissioning procedure, controlling at the source
GB/T 3853-2010 Displacement compressors - Acceptance tests