E46-421 · Commissioning & Run-In · CNC lathe guideway · ★★
The new machine was used for finish machining right away; because the guideways were not run in there were few contact points, and after two months of operation the positioning accuracy went out of tolerance and workpiece size scatter became large.
[Mechanism] Without uniform contact points being developed on the guideway surfaces, local pressure is high and plastic deformation occurs early.
[Calculation] With fewer than 4 contact points per 25 mm² the load is uneven and the surface sinks.
[Design gap] No low-speed full-stroke run-in was scheduled.
① Low-speed run-in: run the guideways unloaded at low speed over the full stroke back and forth several dozen times
② Coat check: use marking compound to check the contact points and extend the run-in if they are few
③ Adjust gibs: adjust the gib tightness during run-in so that the contact is even
④ Measure temperature: feel the guideway temperature rise and stop to cool before continuing if it overheats
⑤ Recheck accuracy: measure the positioning accuracy after run-in and start machining only once it meets the requirement
⑥ Record: record the number of run-in strokes and the contact points
⑦ Quality verification: confirm acceptance by contact points and accuracy, confirmed by data
⑧ Standardize process: write guideway run-in into machine-tool commissioning, controlling at the source
GB/T 17421.1-1998 Test code for machine tools - Part 1: Geometric accuracy