① Determine the output speed n2 and the output torque T2
② Calculate the reduction ratio i=n1/n2
③ Calculate the required power P=T2×n2/9550
④ Determine the service factor f=daily running hours × starting frequency
⑤ Verify the radial force (overhang / axial)
⑥ Confirm the mounting method (foot / flange / hollow shaft)
Case: T2=100Nm / n2=60r/min / i=25 / continuous operation
P=100×60/9550=0.63kW → select a 0.75kW geared motor
① Splash lubrication (most common): the gear dips into the oil / oil is thrown up by gear rotation
• Applicable: pitch line velocity ≤12m/s
② Pressure lubrication (forced): external oil pump
• Applicable: high speed (>12m/s) / high power (>100kW)
③ Grease lubrication: grease fill
• Applicable: low speed (≤2m/s) / intermittent operation
Oil level inspection: reducer oil sight glass / oil level gauge (check with the machine stopped)
Oil change interval: 500h initially / 3000~5000h thereafter
Connection to the motor: align with an elastic coupling
• Concentricity ≤0.05mm (use a laser alignment tool)
• End face gap per the coupling catalogue
Connection to the load:
• Chain drive → sprocket face parallelism ≤0.5mm/100mm
• Belt drive → pulley center distance parallelism
• Gear drive → gear face-width alignment
Mounting bolts: grade 8.8 or higher / torque per the catalogue / fit spring washers
① The output shaft requires high coaxiality with the load shaft
② Use a locking disc / key connection during installation
③ Tighten the locking disc bolts in sequence / to the specified torque
④ Avoid hammering during installation (it damages the bearings)
⑤ Check the shaft end clearance (thermal expansion allowance)
Disassembly: use a hydraulic puller / a dedicated puller (never hammer directly)