Pitfall: more than 10 elbows per 10m of piping
Consequence: high local pressure loss → low system efficiency / heat
Correct practice: reduce the number of elbows / elbow radius ≥3× the pipe diameter
Pitfall: air lines are laid directly on the floor / no drainage slope
Consequence: condensate cannot drain → water enters the pneumatic components
Correct practice: run them overhead / provide a 1/100 slope / fit a drain valve at the lowest point
Pitfall: hydraulic hard pipe is welded and bent on site (not pre-bent)
Consequence: welding slag remains in the pipe → contaminates the system
Correct practice: factory pre-bending / pickling / phosphating / blow clean before installation
Pitfall: compressed-air lines are tied together with power / signal cables
Consequence: when an air line bursts, water and air enter the electrical parts → short circuit
Correct practice: run air lines and power cables separately (spacing ≥100mm)