① Pitfall: Pipe routing is too complex
Correct practice: Simplify the piping as much as possible, reducing elbows and fittings
② Pitfall: The return line is not extended below the oil level in the tank
Correct practice: Extend the return line to at least 2/3 below the oil level
③ Pitfall: Suction line diameter too small
Correct practice: Suction line flow velocity ≤1.5m/s
④ Pitfall: No air vent designed
Correct practice: Install a vent valve at the highest point of the system
⑤ Pitfall: Filter installed in an improper location
Correct practice: Combine a return filter with a high-pressure filter
⑥ Pitfall: Internal oil passages cross in the manifold block
Correct practice: Lay out the passages in layers to avoid crossings
⑦ Pitfall: Oil tank volume too small
Correct practice: Oil tank volume ≥3~5 times the system flow rate
⑧ Pitfall: Oil temperature control not considered
Correct practice: Fit a cooler on high-power systems and control the oil temperature ≤60℃