MOULDLKnowledge BaseElectrical Knowledge Base3D Model DownloadsMembership
中文版Model Store »
Knowledge Base › Electrical Knowledge Base › Interlock before or after the self-latch branch: what differs
HomeModels
Table of contents

On this page

Electrical Control & Drawings (500 articles)

Quick Reference

Interlock before or after the self-latch branch: what differs

Both interlock and self-latch contacts sit in the coil branch, but their position changes behavior. This article clarifies the logic difference between placing the interlock contact before and after the self-latch, and its effect on start-stop and interlock reliability.

1. How it works

Self-latching parallels the contactor own NO auxiliary across the start button to hold after release; interlocking series the opposite contactor NC contact in the coil branch to cut the other. Both are in the same branch, but self-latch is parallel hold while interlock is series break, and their order affects the state after de-energizing.

2. Practice and pitfalls

Placing the interlock toward the supply side and the self-latch toward the coil means the interlock breaks the whole branch, so when it opens the self-latch also releases immediately, a more thorough cut. Placing it just before the coil still breaks the coil logically but may release with slight delay when the interlock opens during a held state. Strictly follow the schematic with interlock before self-latch for clarity and easier fault analysis.

3. Interlock vs self-latch position

PositionConnectionFeature
Interlock frontSeries at supplyCleaner cut
Interlock rearSeries at coilSlight delay
Self-latchNO parallelHold on release
InterlockNC seriesCuts opponent
StandardInterlock frontEasy analysis

4. Notes

Although both sit in the coil branch, placing the interlock in series before the self-latch is more standard and cuts more thoroughly. Follow the schematic order strictly so the interlock sits toward the supply side, ensuring reliable action and simpler troubleshooting.

5. References

The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Low-voltage switchgear per GB 14048.4, control circuit devices per GB 14048.5, referencing IEC 60947-4 and IEC 60204-1. Always check the device datasheet and the product design file for ratings and derating.

6. Cautions

⚠️ Three common pitfalls:
① Interlock after self-latch delays release, not standard
② Mixing opponent NC into own coil becomes self-latch
③ Ignoring drawing makes interlock intermittent

Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.