Drawings rule design and sleeves rule construction, but whether the hardware is right is settled by field verification. This page covers what to check, how to measure and how to record before power-on.
Three timing points: per-loop self-check after cabling, proportion-based sampling at QC acceptance, and 100 percent on critical loops (mains, emergency stop, safety interlocks) before power. Main and e-stop loops are never sampled since one wrong wire is a safety event; control loops sample 10 to 20 percent, prioritising wires that cross strips, pages and cabinets where errors cluster.
Three-step method: look, sleeve versus drawing, clear text at both ends; measure, buzzer from start terminal to end terminal confirming physical continuity and matching numbers; cross-check against the schematic that the link should exist (a wire can ring through yet land in the wrong place). Beware parallel energy-storing elements (capacitors, parallel coil paths) faking continuity on the buzzer. Cross-cabinet wires verify the far cabinet too. Record on a check sheet (wire, both terminals, result, checker, date), tag problem wires red with a hold card, re-verify after fixing, and when one error appears widen the sample along the same fitter and time window until twenty straight wires pass.
| Loop | Coverage | Method |
|---|---|---|
| Mains | 100% | Look meter photo |
| E-stop safety | 100% | Every wire |
| Control | 10-20% | Three steps |
| Cross-cab | Priority | Both ends |
| Problem wire | Red tag | Fix recheck |
| Record | Check sheet | Archive |
Verify at self-check, acceptance sampling and 100 percent on critical loops before power. Three steps: look at sleeves, measure continuity end to end, cross-check the schematic, minding parallel capacitors that fake the buzzer. Log on a check sheet, tag and hold problem wires, and widen the sample after any error until twenty consecutive wires pass.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Installation per GB 50168, safety per GB/T 5226.1, wires per IEC 61175. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.