You reroute one wire but forget the wire number; next service, the old number on the drawing leads nowhere and risks a wrong connection. Wire numbers must move with the revision.
A wire number is the only link between the field and the drawing, so the schematic, the wiring diagram and the markers in the panel must agree. When a change moves a wire, terminal or function, updating only the drawing leaves the old marker in place; maintenance then cannot match the drawing to the field, costing time at best and causing a wrong terminal or short at worst. A change order must treat wire-number update as mandatory, not optional.
The proper flow: change approved, schematic edited, EPLAN/CAD renumbers the affected wires, new wiring diagram exported, fresh markers printed and fitted, old markers removed, drawing revision bumped (A to B) with sign and date. The key is to put wire-number change into the change note with its scope (which cabinets, which terminal strips), signed off by both the installer and the document owner, so the field and the paper never drift.
| Step | Action | Owner |
|---|---|---|
| Review | Approve and issue | Design |
| Edit schematic | Renumber wires | Design |
| Export wiring | New number list | Design |
| Refit markers | Old out new in | Field |
| Revise drawing | A to B sign date | Docs |
| Two-party | Fit and docs sign | Both |
Rule: change order drives it, numbers follow the drawing, revisions are controlled. Change one, check the cluster, swap old markers for new, bump and sign the revision, both parties confirm and file it. Put number update in the change loop so the field never lags the paper.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Electrical documentation per GB/T 6988 series, graphical symbols per GB/T 4728, machine electrical documents per GB/T 5226.1. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.