Setting time intervals in sequential starting circuits

Sequence delays are not picked by feel: too short and the rear motor starts before the front one is stable, too long and the production rhythm drags while motors idle. This page gives three rules and typical values for interval setting.

1. How it works

Rule one, process readiness: the rear unit starts only after the front one establishes its condition — a fan needs 5 to 10 s to open the duct, a pump needs pressure built. Rule two, clear the starting transient: wait until the front inrush has decayed to steady state, 1 to 3 s for small motors, up to 8 s for large ones, so starting surges never stack. Rule three, protection coordination: keep intervals below the process wait limit while spreading thermal accumulation, typically 3 to 15 s stepping up per stage.

2. Numbers and practice

Work from the process backward, then verify on site. Belt example: start the tail belt first, 5 s later the middle, 5 s later the head — starting against material flow, stopping with it. Measure the starting transient: the earliest legal moment for the next stage is when current falls under 1.2 times rated; a 7.5 kW DOL motor finishes within 2 s. Set each KT to the larger of the two plus 1 to 2 s of margin, then trim against the real current curve and archive the values.

3. Pitfalls and fixes

Symptoms of too short: a near-short-circuit current peak at start, occasional upstream breaker trips, contactor chatter on the voltage dip. Symptoms of too long: operators complain about start waits and idle motors burn energy with total start time beyond one minute. Either symptom sends you back to the three rules; after any KT change, redo the cascade and overload linkage tests.

4. Reference intervals for sequential starting

EquipmentSuggested intervalBasis
Multi-belt line5-10 stension built against flow
Fan then process load8-15 sduct condition established
Pump group3-8 spressure and water hammer
Crusher before feeder10-20 sempty-chamber warm run
Motors under 7.5 kW3-5 stransient decays within 2 s

5. Notes

Record every interval with date and version; recheck after any process change or motor swap. Remember intervals accumulate — a five-stage chain at 8 s each spreads 32 s from first to last, so time the whole start with a stopwatch on tight rhythms.

6. References

The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Starting and protection per GB/T 5226.1, timers per GB/T 14048.5. Always check the device datasheet and the product design file for ratings and derating.

7. Cautions

⚠️ Three common pitfalls:
① Interval shorter than the front transient: surges stack and trip, measure the current curve first
② Copying another line values: different conditions break the cascade, set every line on its own
③ Changing KT without records: drawings and dials drift apart, keep the archive in step with the panel

Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.