Six leads and one wrong connection can mean no torque or a burned winding. This page explains the internal structure of a two-speed stator, the terminal marking rules, and a multimeter procedure that identifies terminals even on nameplate-lost old motors.
Each phase of a two-speed stator consists of two identical half-windings, three phases and six leads in total. In the low-speed delta the two halves of each phase connect in series with aiding magneto-motive force, giving four poles; in the high-speed double star the halves parallel with opposing arrangement, halving the pole count and doubling the speed. Polarity is the crux: reversing a half-winding direction turns the high-speed tap into a many-pole running condition with surging current and rapid heating. The half-windings share turns and wire gauge, and the insulation is designed for full voltage in either connection.
Under GB/T 1971 the six terminals read U1V1W1 and U2V2W2, the first ends of the first and second half-windings, with tail ends joined inside the machine. Delta: power on U1V1W1, short U2V2W2 together. Double star: power on U2V2W2, short U1V1W1 into a neutral. The terminal box usually carries a connection plate and links: one three-pole link shorts U2V2W2 for delta; three single links join same-phase pairs and then the three first ends for double star. Wrong link placement silently changes the connection, so verify every link against the nameplate diagram before energizing.
For a nameplate-lost motor, identify in three steps. First, split phases: measure resistance between all terminal pairs; same-phase pairs read a few ohms while different phases read open. Second, fix polarity: use the battery-tap method, momentarily touching a battery across one winding while watching a millivoltmeter on the other, grouping leads by consistent deflection direction and repeating to confirm. Third, verify: wire the delta and run from a 36V safety transformer, checking the three currents balance within ten percent; then convert to double star and check high-speed current and rotation. Any anomaly stops the procedure for re-checking, never guessing.
| Step | Operation | Pass criterion | On failure |
|---|---|---|---|
| Split phases | Resistance between all pairs | Same phase conducts, phases open | Suspect short, send for winding test |
| Fix polarity | Battery tap, watch deflection | Same-phase directions consistent | Repeat with reversed battery |
| Delta verification | Run on 36V supply | Currents balanced within 10% | Re-check polarity on imbalance |
| Double-star verification | Reconnect and run | Normal current, correct rotation | Swap any two supply leads |
| Link check | Compare with nameplate diagram | Every link matches the drawing | Remove, refit, record |
| Insulation check | 500V megger to frame | At least 1 megohm | Dry out before any test run |
Follow this flow for both old and new machines. The discipline is criteria at every step and a full stop on any anomaly: energizing a wrongly connected winding is irreversible, while a few minutes of resistance measurement and low-voltage trial buy a certain first-time success.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Terminal marking and rotation direction follow GB/T 1971; motor test and insulation measurement methods refer to GB/T 1032 and GB/T 5226.1. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.