Where does the control circuit take its power: straight from the mains, through a control transformer, or from a separate DC supply? The choice decides safety, reliability and maintenance risk. This page compares the options and their trade-offs.
Three supply patterns dominate. Direct tapping from two phases or phase-to-neutral of the main circuit is cheap and common on small machines, but the control wiring then sits at 380V or 220V. A control transformer stepping down to 110V, 48V or 24V isolates the control side, improving both safety and interference immunity, and is standard on medium and large equipment. A separate supply such as a DC24V switch-mode unit or UPS serves PLC and safety circuits with the highest reliability. Cost and reliability rise in that order.
With a transformer, mind three points. Size it at 1.5 to 2 times the sum of the holding powers of everything that can be energised together; 250VA and 500VA are common. Decide the earthing: earth one secondary terminal so any earth fault trips, or float the secondary with insulation monitoring. Fit fuses or a breaker on the secondary sized to the largest inrush, or a short circuit will burn the winding; a shield between windings, earthed, improves noise behaviour.
Tap the control supply downstream of the main isolator, so opening the main switch kills the control circuit too and maintenance is safe. Never tap upstream: with the main switch off, live control wiring is a classic shock hazard. On multi-motor machines, feed each motor control branch from the control busbar with its own fuse so one shorted branch does not spread. Mark the tapping point clearly on the drawing; unclear supply points are a standard review finding.
| Option | Typical voltage | Merit | Watch out |
|---|---|---|---|
| Direct tap from mains | AC380V/220V | No transformer, low cost | Control wiring at hazardous potential |
| Control transformer | AC110/48/24V | Isolation, safety, immunity | Size 1.5 to 2 times load |
| DC24V switch-mode | DC24V | PLC-friendly, reliable | Consider redundancy and fusing |
| Independent UPS | AC220V | Holds safety circuits through outages | Costly, fit only as needed |
| Dual transformers | AC220V | Redundancy for key machines | Test the changeover logic |
Fix the supply scheme at concept stage and label transformer rating, ratio, secondary earthing and fuse sizes on the drawing. Maintenance procedures must state which switch to open before the control circuit is truly dead.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Control supply and safety requirements per GB/T 5226.1; control transformers per GB/T 1094 series. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.