Coordinating star-delta and sequence start delays

One machine with both star-delta and sequence start: if the two delays are set independently and ignore each other, swap shock and start shock stack. This note covers the coordination: star-delta by speed, sequence by current peak, and staggered layout of multi-machine delays in one panel, so no collision.

1. How it works

Star-delta delay T1 bases on single motor acceleration, swap after speed, heavy load 8 to 10 seconds. Sequence delay T2 bases on avoiding stacked start current, next after previous peak, 2 to 5 seconds. Different physics: T1 on single speed, T2 on multi current. Set each by its basis first, then place on one time axis to see staggering.

2. Practice and pitfalls

In one machine first star-delta start machine one, then KT sequence start machine two, arrange T1 and T2 as steps: after machine one swap completes, T2 timing starts machine two, avoiding swap instant and start instant current stacking. Same-panel many machines, order by load size, big first small later, each interval T2, total inrush peak cut into segments. Principle: fewest machines moving at any instant, peaks not stacked. Setting: first single tune T1 smooth swap; then T2 stagger peaks; finally whole start, clamp-meter total inrush peak, confirm stepped not stacked over limit. Accept simulate start orders and single faults, delays still hold; log T1 T2 and order, reproduce on maintenance, do not tune by memory. Debug single before total, dead before live.

3. Delay coordination sheet

ParamBasisTypicalLayout
T1 SDSingle speed8-10sFirst
T2 seqPast peak2-5sLater
StaggerNo stackStepFewest
OrderBig firstSmall laterGap T2
AcceptClamp peakStepNo over
LogT1 T2ReproduceNo random

4. Notes

Star-delta T1 by single speed heavy 8 to 10 s, sequence T2 by current peak 2 to 5 s, different basis. Coordinate as steps, swap and start instants staggered, big first small later interval T2, fewest moving at once, peaks not stacked. Accept clamp-meter peak stepped.

5. References

The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Motor start and coordination per GB/T 5226.1 and GB 755, IEC 60204-1. Always check the device datasheet and the product design file for ratings and derating.

6. Cautions

⚠️ Three common pitfalls:
① T1 T2 no coord: stack
② Many moving: peak over
③ Tune by memory: chaos

Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.