Sequential starting is the basic hands-on exercise for trainee electricians: two or more motors start in process order, and the rear contactor may energize only after the front one has sealed in. This article walks through wiring steps, three-stage commissioning and typical fault criteria.
Lay out KM1 and KM2 contactors, FR1 and FR2 thermal relays and three pushbuttons on the bench. Wire the control circuit row by row from the schematic: SB2 drives the KM1 coil, one KM1 auxiliary NO parallels SB2 for self-hold, another KM1 NO sits in series with the KM2 branch as cascade, and SB3 starts KM2. Fit identical wire-number sleeves on both ends of every conductor so wiring always follows the print.
Commission in three stages. Dead control test: power the control circuit only, SB2 picks and seals KM1, SB3 then picks KM2; pressing stop drops KM1 and KM2 releases with it, proving the cascade link. No-load run: connect the motors, jog and read balanced three-phase current around 30 to 50 percent of rated. Loaded run: step the load up over 5 to 30 minutes and watch the thermals for nuisance trips.
Classic faults: self-hold paralleled across the stop button keeps the contactor stuck in; the cascade NO wired after the KM2 seal contact kills the linkage; thermal relays miswired into the control circuit instead of their main contacts. Verify each item before energizing the load.
| Step | Action | Pass criteria |
|---|---|---|
| 1 Dead control | control power only, press SB2 SB3 | KM1 picks and seals first, KM2 follows |
| 2 Cascade check | press SB1 to drop KM1 | KM2 releases together with KM1 |
| 3 No-load run | connect motor, jog and read current | balanced phases, 30-50% rated current |
| 4 Loaded run | step load over 5-30 minutes | current within rating, no nuisance trips |
| 5 Undervoltage check | open and reclose supply while running | motors must not restart by themselves |
After wiring, recheck sleeves, tight terminations, green start and red stop buttons, and prove the E-stop kills both contactors. The same sequence suits belt and crusher lines on site.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Symbols per GB/T 4728, control safety per IEC 60204-1. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.