On-delay and off-delay timers sound alike but their action and wiring are opposite; buy or wire wrong and the machine runs backwards. This note clarifies the timing, contact symbols, wiring and selection so the delay direction is never reversed.
On-delay: when coil energised the delay contacts start timing and act at set time, coil de-energised resets at once. Off-delay: coil energised moves contacts at once, de-energised starts timing and resets at set time. One line: on-delay waits on energise and returns at once on loss; off-delay acts at once on energise and waits on loss. They are exact mirrors; first decide which timing you need, then order.
On drawings the on-delay contact symbol has a clock with an arrow pointing toward the contact, off-delay arrow leaving. Both KT coils connect to control supply, but the delayed contacts go in different branches: on-delay for branches that connect after energise delay, such as star-delta KT delaying open star and close triangle; off-delay for branches that disconnect after de-energise delay, such as post-stop fan delay. Wired reversed the machine delays when it should not and vice versa. Select on-delay for wait after energise, off-delay for run after de-energise, cooling fan or holding valve. Common errors: buying off-delay as on-delay so the fan stops at once; contact type reversed; time unit wrong seconds as minutes. Mark KT type and direction on the diagram, accept with a stopwatch confirming direction and value.
| Item | On-delay | Off-delay |
|---|---|---|
| Energise | Start time | Act at once |
| De-energise | Reset now | Start time |
| Use | After on | After off |
| Example | Star-delta | Cooling fan |
| Symbol | Arrow to | Arrow from |
| Accept | Stopwatch | Dir value |
On-delay waits on energise resets on loss, off-delay acts on energise waits on loss, mirrors. Choose by needed timing, mark type and direction on diagram, accept with stopwatch for direction and value.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Timer per GB/T 5226.1, symbol per GB/T 4728, IEC 60204-1. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.