Phase lines, neutral and protective earth each have their own designation, and a swapped phase sequence reverses motors. This page explains the L1 L2 L3, N and PE notations of GB/T 4728 and how to keep sequence, earthing and colour marks consistent.
A three-phase AC system is designated by letters plus the conductor symbols: phases L1, L2 and L3 (older drawings used A, B and C), neutral N, protective earth PE. The source end shows a circle with the AC mark or the voltage such as 380/220V. The three phase lines run in parallel annotated L1 L2 L3, and the standard requires the sequence to run left to right or top to bottom so a reader can judge phase order directly from the sheet. Never shuffle the three designations.
The protective conductor PE is drawn as a line ending in the earth symbol; a combined PEN line is marked PEN; the system type (TN-C, TN-S or TT) is stated at the main incomer. Equipotential bonding is a horizontal line with the earth symbol. These notations decide how equipment is earthed and whether residual current protection can trip reliably. The PE line must run unbroken from source to earth bar, and it may join N only at one declared point of the TN-C-S transition.
| Conductor | Letter code | Old code | Colour mark |
|---|---|---|---|
| Phase line 1 | L1 | A | yellow |
| Phase line 2 | L2 | B | green |
| Phase line 3 | L3 | C | red |
| Neutral line | N | N | blue |
| Protective earth | PE | PE | yellow-green |
Keep the L1 L2 L3 order strict because a reversed sequence reverses motors and makes pumps run backwards. The PE line must be continuous to the earth bar, and N may meet PE only at the declared point. Colour marks go into the material list and the crew wires by colour.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Supply and conductor symbols per GB/T 4728.3; system earthing per GB/T 16895 and IEC 60364 series. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.