The first energising of a new or repaired panel is the most dangerous step, and one mistake blasts the circuit. This page sets out the standard safety sequence for commissioning.
Before energising confirm all wiring follows the drawing, terminals are tight, no tools or debris remain; megger the main and control circuits and pass; check supply phase sequence and voltage against the nameplate; disconnect all loads (release motor belts or prepare jogging); confirm E-stop, limits and protection settings are in place; post warnings, assign a guardian and add temporary fusing or current limiting. Verify the upstream switch is open and test for voltage first. Skipping this preparation causes most energising accidents.
Never energise everything at once. First feed control power, for example the 24 V, 110 V or 220 V control transformer, verify control point voltages with a meter, and test each button and relay logic one by one. Only after the control circuit is proven, feed main power: jog first (instant close-open) to check rotation and noise, then run briefly, then load. After each step watch current, temperature and smell, opening the switch at any anomaly. Commission drives by setting motor parameters and autotuning before trial.
Field mistakes: closing the upstream switch without verifying voltage, one wrong phase or hidden short and it explodes; energising without insulation test, dampness or damage blasts immediately; loads not disconnected, the motor suddenly turns and hurts people or equipment; no guardian and no reachable E-stop, nobody cuts power in time. Do it right: stepwise energising, control before main, jog first, guardian assigned, E-stop ready; after commissioning restore temporary changes, remove tags and fill records. Post the procedure on the cabinet door so everyone follows it.
| Stage | Action | Key point |
|---|---|---|
| Pre-check | Verify megger | Test dead |
| Control feed | Check logic | Control first |
| Main feed | Jog rotation | Main after |
| Loaded | Short to normal | Observe |
| Close-out | Restore untag | Fill log |
Safe commissioning means pre-checks with insulation and dead verification, stepwise energising control before main, jogging first, and a guardian with E-stop ready. Watch each step and open on anomaly; drives autotune first. Post the procedure on the cabinet and new staff can commission safely.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Electrical safety see GB/T 5226.1 (IEC 60204-1) and GB/T 13869, commissioning see relevant codes, low-voltage apparatus see GB/T 14048. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.