Testing a reversing circuit out of order risks inaccurate results or burned equipment. This article gives a standard five-stage flow: dead wiring check, insulation test, no-load function test, limit verification and loaded trial, with the items, pass criteria and safety measures of each stage listed for one-pass commissioning.
Before power: two jobs, wire check and insulation. Verify every contact type and series-parallel relation with a buzzer meter, focusing on interlock NCs and the main-circuit cross; measure phase-to-phase and phase-to-earth insulation of the power circuit with a 500 V megger, at least 0.5 megohm, control circuit likewise. Dry out or trace any damp point rather than energizing a doubtful circuit, and confirm terminal torque, earthing and no leftover tools inside the cabinet.
No-load test with the motor leads removed: energize the control circuit and run five checks in order: forward button picks and latches KM1; stop releases it; reverse button picks and latches KM2; pressing the other direction while running gives the designed changeover; and above all, pressing both buttons closes neither contactor. Listen for crisp, chatter-free action. Verify limits in the same stage: trip each limit by hand and the corresponding contactor must drop at once. Loaded trial follows: jog to confirm both directions match the process, run and check the three-phase current balance within ten percent, then run under normal load watching current and temperature rise. Fill the commissioning record with insulation values, action results and current data; any failed item stops the sequence until fixed and retested from that stage.
| Stage | Main items | Pass criterion |
|---|---|---|
| Dead wiring check | Buzzer point by point | Matches drawing |
| Insulation test | 500 V megger | At least 0.5 megohm |
| No-load test | Including both-press | No simultaneous close |
| Limit verification | Manual trip | Direction releases |
| Loaded trial | Current and heating | Within rated values |
The order is the safety order: dead hardware check, no-load logic, loaded running; stages cannot be swapped or skipped. The no-load both-press test is the final verdict on the interlock and must precede any load. Archive honest records; they are the baseline for future maintenance.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: See GB/T 5226.1 for machinery safety, GB 14048.4 for apparatus, GB 50303 for installation acceptance, IEC 60204-1 for reference. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.