Numbers dumped into one block leave no room to insert new wires and tell nothing about the loop class. This page covers zone division thinking and a reference block allocation that turns numbers into a map of the cabinet.
Divide along three dimensions: voltage or class (power, AC control, DC, analogue, comms each owning a block); space (in-cabinet, cross-cabinet interface, field boxes); and function (safety, interlock and alarm sub-zones inside a class block, e.g. safety on 150 to 159). Stack the dimensions: class first then function, and keep buffers between blocks so growth never crowds a neighbour.
A reference allocation, adjustable per cabinet type: 1 to 99 mains; 100 to 149 AC control main branches; 150 to 159 safety and e-stop; 160 to 199 AC control auxiliary; 200 to 249 DC 24 V; 250 to 279 DC interlock and alarm; 300 to 349 analogue inputs; 350 to 399 analogue outputs and comms; 900 to 999 cross-cabinet interface and reserve. Reserve about 20 percent inside each block, issue the allocation table at project start for all designers to draw from, expand blocks tailward only when 80 percent used, register temporary commissioning numbers and release them, and migrate legacy messy numbering loop by loop on retrofits with a check after each migration.
| Block | Use | Note |
|---|---|---|
| 1-99 | Mains | Phases |
| 100-149 | AC main | By branch |
| 150-159 | Safety e-stop | Dedicated |
| 160-199 | AC aux | Interlocks |
| 200-249 | DC 24 V | Odd even |
| 300-399 | Analogue comms | In and out |
| 900-999 | Interface | Cross-cab |
Divide blocks by class, space and function with a dedicated safety block and reserved percentages; issue the allocation table first, expand tailward at 80 percent, register and release temporary numbers, and update the table with each retrofit via change control.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Documents per GB/T 6988, marking per GB/T 4026, wires per IEC 61175. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.