Rows of contactors fill a coordinated panel; how do you size each one, set the category and leave margin? This page walks the sizing workflow for coordination duty: per-machine calculation, simultaneous pickup, changeover duty and spare unification, with a worked example table.
Each contactor is sized independently: take the nameplate current, set the base by utilization category (AC-3 for direct-starting cage motors, AC-4 for frequent jogging), apply a 1.1~1.2 margin and round up to the standard frame. Coordination adds duty combinations: simultaneously started groups verify making capacity against stacked inrush (AC-3 requires making at eight times rated working current); sequenced chains verify breaking duty, distinguishing loaded from unloaded breaking and checking the loaded case against AC-3 breaking ratings. Breaker, contactor and thermal relay coordinate in a current ladder, short-circuit above switching above overload, with no crossing settings.
Simultaneous pickup checks two things: the stacked starting current hitting the supply, which sizes breakers and transformer while each contactor still follows its own motor; and the control-circuit VA of several coils picking up together, which sizes the control transformer. Changeover duty: in sequenced chains the upstream contactor breaks loaded current at every switch, so contact life is discounted by break count, and links switching more than ten times per hour take heavy-duty types or one frame up. Two-speed coordination treats KM1 (breaking loaded low-speed current) differently from KM2, each verified on its own duty. Record five columns on the selection sheet: station, nameplate current, category, frame, and verification conclusion.
Spare strategy: unify models where frames are close (use a 12A frame for both 9A and 12A duty) to halve spares and lift interchangeability; one coil voltage across the panel; uniform auxiliary contact blocks. Layout affects sizing: dense mounting below fifty-millimeter spacing derates five to ten percent, hot shops take a higher insulation class. On delivery verify model, coil voltage and accessories, and archive coil and contact resistance per unit. One selection sheet fixes every parameter for purchasing, acceptance and repair alike.
| Station | Nameplate current | Category | Frame after margin |
|---|---|---|---|
| M1 pump 3kW | 6.8A | AC-3 | 9A frame |
| M2 conveyor 5.5kW | 11.5A | AC-3 | 16A frame |
| M3 main 15kW | 30A | AC-3 | 40A frame |
| M4 fan 7.5kW | 15A | AC-3 | 18A frame or larger |
| M5 discharger 2.2kW | 5A | AC-3 | 9A frame |
| Panel unification | — | — | 12A/18A/40A three frames |
Replace the currents with your own and the table becomes your sizing example. Three points carry it: size each machine independently, verify changeover duty separately, unify frames to cut spares; the selection sheet is the single source of truth for purchasing, acceptance and repair.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Contactor utilization categories and ratings follow GB/T 14048.4 (IEC 60947-4-1); motor ratings refer to GB/T 755. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.