MOULDLKnowledge BaseElectrical Knowledge Base3D Model DownloadsMembership
中文版Model Store »
Knowledge Base › Electrical Knowledge Base › Reading trip curves and short-circuit coordination
HomeModels
Table of contents

On this page

Electrical & Electronic Basics (600 articles)

Quick Reference

  • PLC & Programming
  • Electrical & Electronic Basics (monthly)(每月更新中)
  • Electrical Control & Drawings (monthly)(每月更新中)
  • Drives & Actuators (monthly)(每月更新中)
  • Sensors & Detection (monthly)(每月更新中)
  • Industrial Communication & Networks (monthly)(每月更新中)
  • HMI & Host Systems (monthly)(每月更新中)
  • Industrial Robots & Motion Control (monthly)(每月更新中)
  • Mechatronic System Integration (monthly)(每月更新中)
  • Fault Diagnosis & Standards (monthly)(每月更新中)

Reading trip curves and short-circuit coordination

The trip curve looks like a spider web but is two lines: overload and short. This page reads the chart and uses it for up/down selectivity.

1. How it works

The trip curve has current multiple (vs In) on the x-axis and trip time on a log y-axis. The left gentle part is thermal (bimetal), inverse-time: 1.2~1.45 In trips in hours, 2 In in tens of seconds, 5 In in seconds. The right steep part is magnetic (solenoid): C type 5~10 In, D type 10~20 In trips within ≤0.1 s. The two meet near 5~10 In. Reading it tells how long a given current takes to trip.

2. Numbers and practice

Selective coordination means on a downstream fault only the nearest breaker trips, not the upstream, avoiding wide blackout. Method: upstream In larger than downstream (usually ≥1.6×), and upstream magnetic threshold above the downstream prospective fault, or use a selective breaker. In time the upstream acts one grade later. Example: downstream C16 trips 5~10 In, upstream C40 with longer time ensures only the 16 A branch clears. Trap: up/down In too close makes both trip on fault and kills the whole section.

3. Pitfalls and fixes

When selecting, overlay the maker curves: place up and down on one chart, confirm at the fault current the downstream has tripped while upstream has not. Motor circuits use D to ride start, both D for selectivity. Rule: two segments, short-circuit reads the instant zone, coordination reads upstream-late. Also confirm breaking capacity (see breaking page). Verify actual trips with a fault recorder.

4. Curve and coordination

ZoneMultipleAction
Thermal1.2~5 InSec~min
Mag C5~10 In≤0.1 s
Mag D10~20 In≤0.1 s
SelectiveUp laterIn≥1.6×
MethodOverlayDown first

5. Notes

The curve splits thermal (inverse 1.2~5 In) and magnetic (C 5~10, D 10~20 In, ≤0.1 s). Selectivity needs upstream In≥1.6× downstream and later action; overlay to confirm downstream trips first. Motors use D to ride start.

6. References

The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Switchgear per GB/T 14048.2; selectivity per GB/T 50054. Always check the device datasheet and the product design file for ratings and derating.

7. Cautions

⚠️ Three common pitfalls:
① Up/down In too close trips both on fault
② No curve overlay fails coordination
③ C curve on motor trips on start

Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.