Knowledge Base › Electrical Knowledge Base › Using an earth resistance tester and the correct measurement steps
HomeModels
Table of contents

On this page

Electrical & Electronic Basics (600 articles)

Quick Reference

  • PLC & Programming
  • Electrical & Electronic Basics (monthly)(每月更新中)
  • Electrical Control & Drawings (monthly)(每月更新中)
  • Drives & Actuators (monthly)(每月更新中)
  • Sensors & Detection (monthly)(每月更新中)
  • Industrial Communication & Networks (monthly)(每月更新中)
  • HMI & Host Systems (monthly)(每月更新中)
  • Industrial Robots & Motion Control (monthly)(每月更新中)
  • Mechatronic System Integration (monthly)(每月更新中)
  • Fault Diagnosis & Standards (monthly)(每月更新中)

Using an earth resistance tester and the correct measurement steps

An earth resistance number is only as good as the electrode layout. This page walks the three pole fall of potential method, the standard spacings, and the acceptance values for each kind of installation.

1. How it works

The three pole method needs the tester, the electrode under test, and two auxiliary spikes in a straight line: the current spike at distance C and the potential spike at P, commonly 20 m and 40 m out for a single rod. Connect the E lead to the earthing conductor, disconnect the equipment side first so parallel paths do not fake a low reading, drive the spikes fully, and keep the line clear of buried pipes and cables that shunt the test current.

2. Practice and pitfalls

Measure at least twice with the potential spike moved a few meters either side; stable readings within 5 percent confirm the flat part of the curve. Acceptance depends on the object: 4 ohms or less for low voltage equipment earths and transformer neutrals, 10 ohms for lightning protection and repeated earthing of the neutral, and for TT systems the value must satisfy R times body current logic, practically under 50 divided by the RCD operating current. Seasonal moisture swings readings by a factor of two or more, so test in the worst dry season where possible and log every result with the weather.

3. Earth resistance acceptance quick table

Object under testAcceptance valueSpike spacing
Low voltage equipment earth4 ohms or less20/40m
TT system with RCDUnder 50/Ia ohms20/40m
Lightning protection earth10 ohms or lessEnlarged per grid
Transformer neutral earth4 ohms or lessEnlarged per grid
Repeated neutral earthing10 ohms or lessAt line ends

4. Notes

Lay the three spikes in a straight line, disconnect the installation before testing, and accept 4 ohms for equipment earths, 10 ohms for lightning protection. Test in the dry season and log results.

5. References

The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Earthing installations follow GB 50169 and GB/T 21431, system earthing GB/T 14050, with test methods per IEC 61557. Always check the device datasheet and the product design file for ratings and derating.

6. Cautions

⚠️ Three common pitfalls:
① Testing with the earthing conductor still connected to the plant grid: parallel paths through cables fake a low reading that hides corrosion
② Leaving the potential spike beside a buried pipe: the pipe shunts test current and the meter reads optimistically low
③ Accepting a wet season reading as proof: resistance doubles in the dry season and the protection silently degrades

Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.