A transistor with no label or one you suspect is bad is no problem with a multimeter. This page gives the practical routine to find the pins, estimate beta and judge good or bad, the same way old hands do it.
Use the diode range. Measure any two leads; a 0.5 to 0.7V forward drop means those two are base and another electrode, leaving the third to test. For NPN the black lead (positive in diode mode) on base and red on C or E each shows 0.7V; for PNP it reverses. The common base shows overload when leads swap, which tells NPN or PNP and the base pin, per GB/T 4728.
With base found, separate C from E by gain: most meters only read in the hFE socket when E-B-C is correct, a reversed insert reads near zero. You can also touch C and E with the diode leads while finger-bridging B-C to see conduction change. Estimate beta directly in the hFE socket; 50 to 300 is normal, near zero or overflow means failure.
Good or bad shows four ways. A healthy part has one 0.7V drop each on B-E and B-C, and C-E is open both ways. Failures: C-E short (conducts) burns at power on; B-E open (both ways OL) never conducts; leakage (unstable reading) is unstable in circuit; breakdown (any two leads connected) is scrap. Test pulled parts before tossing them.
| Test | Normal | Fault read |
|---|---|---|
| B-E | 0.7 V one way | both OL open |
| B-C | 0.7 V one way | connected short |
| C-E | both OL | conduct short |
| hFE | 50 to 300 | 0 or over bad |
| Polarity | black on B NPN | reverse PNP |
| Leak | unstable | unstable work |
This fits field repair, spare screening and salvaging old boards. Find the base first, then split C and E, confirm beta in hFE, and class bad parts by the four signs. Remember the diode-mode polarity: on a digital meter red is negative and black is positive.
The quantities and component characteristics discussed here follow current national standards and the corresponding IEC documents: Device test and symbols per GB/T 4728; safety IEC 60204-1. Always check the device datasheet and the product design file for ratings and derating.
Locate the issue with the approach above, then confirm with measurements; safety-related circuits must follow the standards and manufacturer requirements.